Rural Broadband Project Timeline and Updates

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

The project will be implemented in five phases over the next three years and will include the following communities:

  • Texas (23 miles): Completed
  • Byrd (9 miles): Completed
  • Gum Branch (15 miles): Completed
  • Cowtails (64 miles/528 homes): Completed
  • Reevesville / Shady Grove (60 miles/828 homes): Completed
  • Indian Field (12 miles): Completed
  • Rosinville (27 miles/810 homes): Completed
  • First and Second Texas (34 miles/466 homes): Completed
  • Gettysville (40 miles/417 homes): Completed
  • Spring Branch (10 miles/171 homes): Completed
  • Thomas Kate Road (9 miles/119 homes): Completed
  • South Dorchester (43 miles/455 homes): Completed
  • Herdons Pond (14 miles/236 homes): Completed
  • Taylors Pond (12 miles/200 homes): Completed

Project Updates

Reevesville
Construction is 100% completed with 23.87 miles completed in the Reevesville area as of July 2023. St. Mark Bowman and Apple Wood are both 100% completed and currently taking service orders. 

Cowtails
Construction is 100% completed with 20.07 miles completed in the Cowtails area. Friendship, Cross Creek, and Durhams Corner are all 100% completed and taking service orders as of September 2023.

Rosinville
Construction is 100% completed with 7.22 miles in the Rosinville area. Mulberry, Rosinville Crossroads, Duncan Chapel, Indian Field Creek, and Mt. Zion are all 100% completed and taking service orders as of September 2023.

Winding Woods
Construction has been completed in the Byrd and Texas areas, and PRCT is currently taking service orders for these areas. The Gum Branch area is currently 94% completed as of July 2023.

Gettysville
Construction has been completed for both County Line and Gettysville. County Line construction is at 100% completion, and Gettysville construction is at 100% completion.

Spring Branch
Construction has been completed, and Home Telecom is currently taking service orders. 

Thomas Kate
Construction has been completed, and Home Telecom is currently taking service orders.

South Dorchester
Construction has been completed, and Home Telecom is currently taking service orders.

Herndons Pond
Construction has been completed, and Home Telecom is currently taking service orders.

Taylor Pond
Construction has been completed, and Home Telecom is currently taking service orders.