Home MenuLand Disturbance and Development Management
Erosion Prevention and Sediment Control (EPSC) Certification
For Single Family Residential Structures (SFR) that disturb less than one (1) acre and commercial, industrial & Major Subdivision that disturb less than one half (0.5) acre, please complete and load the following items into Evolve:
- Erosion Prevention and Sediment Control Certification, completed and signed.
- A narrative briefly explaining the project.
- Drawings showing the proposed project limits and during-construction erosion and sediment controls.
- $100.00 EPSC Fee.
Stormwater Construction Approval Application
For Single Family Residential Structures that disturb one (1) acre or more and commercial, industrial, & Major Subdivisions that disturb one half (0.5) acre or more, please complete and load the following items into Evolve:
- Stormwater Construction Approval Application (CAA)
- Operating and Maintenance Agreement of Stormwater Facilities
- Pond Maintenance Plan
- Construction Plans and Applicable Schematics
- Construction Approval Application Checklist
- Stormwater Review & Inspection Fees (refer to the following table)
Major Modification Application
For Major Modification applications, please reference the below documents. After submitting SCDHEC's Major Modification application to SCDHEC, please upload the application to Evolve. Please complete Dorchester County's Stormwater Major Modification Application and all other required supporting documentation and then upload to Evolve.
Plan Review and Inspection Fees
A non-refundable permit fee, as designated from time to time by County Council, shall be collected at the time the stormwater management plan or application is submitted. The permit fee shall provide for the cost of plan review, administration, and management of the permitting process, and inspection of all projects subject to this Ordinance. A permit fee schedule shall be established by the County Council based upon the relative complexity of the project and may be amended from time to time.
Fee Schedule for Stormwater Plan Review:
TYPE OF Development | dISTURBED aCRES | 1ST REVIEW | 2nd review | 3RD rEVIEW | 4TH rEVIEW | |
---|---|---|---|---|---|---|
Residential - Individual Single Family | Less than 1 Acre | $100 Flat Fee | No Fee | No Fee | No Fee | |
Residential - Individual Single Family | 1 Acre or Greater | $200 (per Disturbed Acre) | $40 | $20 | $20 | |
Residential - Single Family Subdivision | 0.5 Acre or Greater | $200 (per Disturbed Acre) | $500 | $250 | $250 | |
Residential - Multi-Family | 0.5 Acre or Greater | $400 (per Disturbed Acre) | $500 | $250 | $250 | |
Non-Residential | Less than 0.5 Acre | $100 Flat Fee | No Fee | No Fee | No Fee | |
Non-Residential | 0.5 Acre or Greater | $400 (per Disturbed Acre) | $500 | $250 | $250 | |
Review of Application for a Variance |
Any |
$600 (per Disturbed Acre) |
$600 per fact finding meeting |
|||
Major Modification |
Any |
$300 (per Disturbed Acre) | $500 | $250 | $250 |
SCDHEC requires a $125 fee to issue an NPDES permit.
In addition to plan review fees, the County has an inspection fee. The County has the authority to require re-inspection fees on any project deemed necessary. The following table includes the construction site inspection fees:
Fee Schedule for Construction Inspections:
Development Activity | Area of Disturbance | Standard Fee |
---|---|---|
Residential - Individual Single Family | Less than 1 Acre | Included in Plan Review Fee |
Residential - Individual Single Family | 1 Acre or Greater |
$200 |
Residential - Single Family Subdivision | 0.5 Acre or Greater |
$2 per linear foot of road + $4 per linear foot of drainage easement |
Residential - Multi-Family | 0.5 Acre or Greater |
$2 per linear foot of road + $4 per linear foot of drainage easement |
Non-Residential | Less than 0.5 Acre | Included in Plan Review Fee |
Non-Residential | 0.5 - 4.9 Acres |
$200 |
Non-Residential | 5.0 - 9.9 Acres |
$400 |
Non-Residential | 10 Acres or Greater |
$800 |
Re-inspection for any reason |
Any size |
$150 |
Traffic Impact Analysis Requirements
Pre-Construction Meeting and Proof Roll Requirements
Preliminary and Final Plat Requirements
Closeout Requirements
- Closeout Checklist
- Closeout Requirements (Residential/Commercial)
- Closeout Application
- Transfer of Ownership (if applicable)
Reference Technical Documents
- Utility Pavement Cut and Repair Guidelines (Updated: Oct 2024)
- Plan Review Flow Chart
- Comprehensive Roads and Drainage Plan Review and RMAA Process
- * Updated Stormwater Ordinance 23-06
- Stormwater Design Manual
- EPA Wet Pond and Wetland Management Guide
- SCDHEC BMP Manual
- SCDHEC Construction General Permit
- SCDHEC MS4 Permit
- Dorchester County NRCS Rainfall Distribution
- Stormwater Design Standards Alternative Pipe Material